|
Critical Chain
Project Management
Critical Chain
Project Management (CCPM) is the first major advance in Project
Management principles since the 1950's. A new paradigm for project
management, Critical Chain in the form of Critical Chain Project
Management provides a highly sophisticated way to plan and manage
risk and reduce project schedules. Planning and tracking will be
easier. You will get more done in less time and complete projects
faster. Critical Chain Project Management has two parts: It applies
to individual projects, and it applies to managing the entire set of
projects in an organization.
What is
Critical Chain Project Management?
- The first
really new way to manage projects in forty years.
- A better way
to achieve project success: scope, cost, and schedule.
- A way to
reduce project duration by one half or more.
- Reduced
stress for project teams and managers.
- Focuses on
the uncertainties in any project
- Centered
around finding the constraints & arranging everything around
them
- Addresses
single-project scheduling and identifies the shortest time that a
project can be delivered considering both task and resources
dependencies
Critical Chain
Project Management is the name of the breakthrough approach to
scheduling and managing projects developed by Eli Goldratt in 1990.
A significant advance over PERT/ CPM, which has been the dominant
approach to PM for more than 50 years, Critical Chain Project
Management addresses some of the most damaging phenomena in managing
projects, including the cascade effect, Parkinson’s law, and
multi-tasking, which drive projects to miss delivery dates, exceed
budgets, and take longer than they should. What make the approach so
successful are its four essential elements.
- Schedules are
level-loaded based on the limitations of available resources
(constraints). This produces the “critical chain”—the longest set
of sequential tasks (due to both task dependency, and resource
contention)—which dictates the shortest overall project duration.
- Time buffers
are inserted at strategic locations in the plan—at the end of the
critical chain and at every point where a task intersects the
critical chain—to absorb the adverse effects of uncertainty
without damaging performance. To create the buffers, some of the
slack time built into tasks in planning is repositioned to these
strategic locations.
- Projects are
“pipelined” or staged based on resource availability to combat the
cascade effect of shared resources across projects and create
viable multi-project plans.
- Buffer
management is used to dynamically set task priorities in
execution. As uncertainty changes the original plan, tasks are
prioritized based on the buffer burn rate (the amount of buffer
consumed vs. the percent of the work complete). Tasks with
critical buffer penetration take precedence over those with lower
burn rates.
Critical Chain
Project Management is enabling organizations to complete more
projects faster with the same or fewer resources. The typical
business results realized are:
- On-time
completion of projects nearing 100% (with no reduction in scope)
- Project
durations reduced 20-60%
- Volume of
projects increased 25-100%
In terms of
operational benefits, companies are
reporting:
- Better
visibility of risk and faster overall response to problems
- Clearer, more
stable priorities
- Stronger
focus and more effective use of resources
- Less overall
administration effort, with better, more up to date
information
For most
organizations Critical Chain Project Management requires a shift in
three areas:
- Measurement-
Common measures like earned value focus on completing any work on
a project—whether it is on the Critical Chain or not. This drives
the completion of “easier tasks” often at the expense of ones more
critical to overall project completion. Similarly a focus on task
completion dates encourages task estimates to be padded, reduces
the urgency to start a task when it becomes available, and
provides no protection for the project when a delay does occur.
Critical Chain Project Management works when an organization
manages according to its buffers and evaluates overall performance
based on the rate at which resources consume or recover the
buffer.
- Information-
The information companies need to make Critical Chain Project
Management work is different from conventional methods. While many
conventional systems can level load resources, none has the
facility to place buffers appropriately, or to provide dynamic
information regarding buffer burn rates. There are a very small
number of systems that even claim to be able to handle these
challenges.
- Decision
processes- To get different results, different decisions must be
made—which means engraining new processes in the organization.
These processes can be well defined and readily taught to key
managers.
Critical Chain
Project Management is based on:
- Common sense
and reality
- How people
work most effectively
- Using
information effectively
- Minimum
schedule complexity that gets the job done with acceptable
risk
- Proven Theory
of Constraints philosophy put to another practice
use
- Simple,
proven methods
- Software that
makes Critical Chain Project Management accessible by
everyone
- One project
alone, or multiple projects sharing
resources
Critical Chain
Project Management does not:
- Require ideal
scenarios, not perfect data
- Make people
work like robots to impossible standards of
perfection
- Create
information overload, nor information vacuum, nor out of date
reports
- Create
analysis paralysis, nor a huge bureaucracy
overhead
- Depend on
impractical nor untested ideas
- Require
project management specialists, nor “rocket
science”
- Have
proprietary technology nor algorithms, everything is “open
source”
- Limit your
flexibility nor responsiveness, it
them
When
you, as a project manager, accept responsibility for a project, you
accept the schedule, timeline, deadlines, resources, and
expectations set out at the start. Now you can make sure you're
asking the right questions for each project by utilizing the tools,
checklists, and information from projectmanagementsurvival.
Now
you can manage your risk project according to best practice
standards. You'll have the details and plans in place to handle
whatever arises during a project's duration—setting appropriate
expectations for timelines, milestones, and deliverables. And,
ensure success for each and every project with resources on:
- Ensuring you
have the necessary equipment and resources available
- Properly
documenting all project activities
- Identifying staff skills by roles needed
- Putting
quality controls in place
- Identifying
and estimating indirect costs
- Documenting
and prioritizing requirements
- And much more
Start and end
each project on a positive note—order your Templates and Tool Kits for Project
Managers today!
Explore the templates and toolkits
HERE |